The newspaper articles about Mojiko Station

② Many workers
多くの従事者
Dated June 1, 1913
多くの従事者
 ▼Transitory translation
Hishikawa-Gumi is working well on the renovation of Moji Station with 50 workers for carpentry, plastering, etc. from 6:30 am to 6:30 pm. Although they take breaks from time to time, there were accidents, so they invited the chief priest from Mekari Shrine to have a ground-breaking ceremony on the 30th to be reassured as a team. The 390 tsubo station building, 648 tsubo platform, 209 tsubo platform, 20 tsubo toilets, and 30 tsubo corridor are nearly completed, so we decided to start from tomorrow the 2nd and will almost complete all the construction before July 10th.